Home  ›  Projects/References  ›  A5 North Highway, Ypsilon
   
 
Downloads
Project sheet -
A5 North Highway

Links
HOCHTIEF PPP Solutions
HOCHTIEF Construction AG
Streif Baulogistik
Asfinag
Bonaventura
A5 North Highway, Ypsilon
Project pictures
Click onto the picture to enlarge it
Outside Vienna, HOCHTIEF Construction Austria is realizing sections of the massive Ypsilon PPP road construction project in a joint venture engaged by the Bonaventura concession company. HOCHTIEF PPP Solutions has a major stake in Bonaventura. The project includes sections of the A5, S1 and S2 highways, which will link the capital with the Weinviertel area. Together, the individual construction sites make up a 51 kilometer section of the north highway and northeastern bypass.

The advantages for the region are obvious: less traffic on narrow country roads or through villages and a faster connection to Vienna and from the capital to the Czech Republic. The improved transport infrastructure will also make Lower Austria a more attractive location for industry and business.

More information about this project you can find in our Project sheet.
Project data
Concession provider:
Autobahnen- und Schnellstraßen-Finanzierungs-Aktiengesellschaft (Asfinag)

Client:
Bonaventura Straßenerrichtungs-GmbH

Contractor (Joint venture):
Arge PPP Ostregion, Alpine –
HOCHTIEF Construction Austria

Concession period:
33 years

Construction period:
2007 to 2010

Operating period:
2010 to 2039

Total costs (incl. financing and operation):
933 million EUR

Construction costs:
approx. 800 million EUR

Technical data
Length of section 51 km
Volume of earth moved approx. 9 million m³
Noise protection measures approx. 81 km
Concrete pavement carriageway 1.3 million m³
Asphalt 380,000 t
Concrete approx. 1.1 million m³
Reinforcement approx. 80,000 t
18 underpasses
76 bridge structures

7.4 km tunnel sections (4 tunnel structures)
with state-of-the-art tunnel equipment
approx. 30 traffic census sections

Control building with highway maintenance unit, complete vehicle pool and own monitoring center
for tunnels

Two service areas with parking spaces for
a total of 400 cars/260 trucks, hotel, seminar
rooms and truck driver rest facilities
 
   