Vienna is getting a new central train station.
On an area totaling 109 hectares, a new mobility center will be built around the
existing South Station.
To allow the removal of the South Station and the start of the actual construction
work, the South and East Stations will be closed in December 2009. A lot of preparatory
work is required for this. A large part of this work, called Provisional Arrangement
1, is being performed by a consortium including HOCHTIEF Construction Austria. This
construction project is divided into three subprojects.
Subproject 1: Truncated East Station (Provisional East Station)
In this subproject, the construction areas in the area of the existing hall of the
South Station and the areas towards Arsenalstraße must be cleared. To allow
continued train operations, a truncated form of the station called "Vienna
South Station East" will be required. This truncated East Station will remain
in use until the new central station starts initial operations (planned for the
end of 2012).
Subproject 2: Provisional east railway yard
The railway yard, with a storage capacity of 3,320 m (10,900 ft) of track, forms
the basis for starting construction of the new through station. This will require
building new below-ground and above-ground structures, laying cables and piping,
and work related to the traffic control system. A wheel washing facility will be
set up near the Vienna South Freight Station road exit to the Sonnwendgasse. In
addition, it is necessary to prepare trenches and conduits for the temporary relocation
of a 55kV line.
|
|
Subproject 3: Bypass track
This subproject is located north of the siding on the site of the former postal
complex. To maintain the connection between the south and east lines, temporary
tracks will be built to replace the existing tracks running through the central
station. Besides earthwork activities, the main task is the construction of a massive
gravity wall.
Additional work includes backfilling the old postal tunnel, constructing portions
of the future sewer system, and installing conduits. Elevated construction roads
will allow safe traffic for all vehicles. Near Südtirolerplatz, pipe jacking
will be used to produce a temporary cable crossing to service the remaining track
facilities.

|
Technical data |
 |
Excavation: 55,200 m³ (1.9 million cu. ft.) |
 |
Backfill: 26,500 m³ (936,000 cu. ft.) |
 |
Piping: 7,200 m (23,600 ft.) |
 |
Formwork: 5,000 m² (53,800 sq. ft.) |
 |
Rebar: 100 metric tons |
 |
Steel structures: 100 metric tons |
 |
Concrete: approx. 6,500 m³ (300,000 cu. ft.) |
 |
Base course, unconsolidated: 9,300 m³
(330,000 cu. ft.)
|
 |
Base course, consolidated: 1,800 metric tons |
|
|