Home | Contact | Downloads | Imprint | Sitemap | Search | German

Current topics Vacancies

A5 North Highway, Ypsilon
LT 31 - Maxing, Lainz Tunnel
Wienerwald Tunnel
B 63 Bypass
Leibnitz Wastewater
Treatment Plant
Reactivation of the Tullner
Westschleife
Reconstruction of Herzogen-
burg Railroad Station
Vienna Central Train Station
Salzburg Main Station
References
Home  ›  Projects/References  ›  Vienna Central Train Station
   
 

Links
ÖBB-Infrastruktur AG
Vienna Central Train Station BL04, Provisional Arrangement 1
Project pictures
Click onto the picture to enlarge it

Vienna is getting a new central train station.

On an area totaling 109 hectares, a new mobility center will be built around the existing South Station.

To allow the removal of the South Station and the start of the actual construction work, the South and East Stations will be closed in December 2009. A lot of preparatory work is required for this. A large part of this work, called Provisional Arrangement 1, is being performed by a consortium including HOCHTIEF Construction Austria. This construction project is divided into three subprojects.

Subproject 1: Truncated East Station (Provisional East Station)

In this subproject, the construction areas in the area of the existing hall of the South Station and the areas towards Arsenalstraße must be cleared. To allow continued train operations, a truncated form of the station called "Vienna South Station East" will be required. This truncated East Station will remain in use until the new central station starts initial operations (planned for the end of 2012).

Subproject 2: Provisional east railway yard

The railway yard, with a storage capacity of 3,320 m (10,900 ft) of track, forms the basis for starting construction of the new through station. This will require building new below-ground and above-ground structures, laying cables and piping, and work related to the traffic control system. A wheel washing facility will be set up near the Vienna South Freight Station road exit to the Sonnwendgasse. In addition, it is necessary to prepare trenches and conduits for the temporary relocation of a 55kV line.


Subproject 3: Bypass track

This subproject is located north of the siding on the site of the former postal complex. To maintain the connection between the south and east lines, temporary tracks will be built to replace the existing tracks running through the central station. Besides earthwork activities, the main task is the construction of a massive gravity wall.

Additional work includes backfilling the old postal tunnel, constructing portions of the future sewer system, and installing conduits. Elevated construction roads will allow safe traffic for all vehicles. Near Südtirolerplatz, pipe jacking will be used to produce a temporary cable crossing to service the remaining track facilities.


Project data

Client:
ÖBB-Infrastruktur Bau AG

Contractor (Joint venture):
Arge Östu-Stettin – HOCHTIEF Construction Austria – Swietelsky

Construction period:
2009 to 2010

Contract amount (net):
EUR 5.9 million


Technical data
Excavation: 55,200 m³ (1.9 million cu. ft.)
Backfill: 26,500 m³ (936,000 cu. ft.)
Piping: 7,200 m (23,600 ft.)
Formwork: 5,000 m² (53,800 sq. ft.)
Rebar: 100 metric tons
Steel structures: 100 metric tons
Concrete: approx. 6,500 m³ (300,000 cu. ft.)
Base course, unconsolidated: 9,300 m³
(330,000 cu. ft.)
Base course, consolidated: 1,800 metric tons

 
   
back print page compile PDF