Construction phases
East heading:
Westwards from Vienna-Weidlingau (2,350 meters double-track tunnel by shotcrete
tunneling (NATM), full section A = 120 - 245 square meters)

Taglesberg landfill:
Creation of an approx. 470 meter long muck gallery for excavated material deposited
by conveyor belt (gradient: 32 percent); placement of approx. 860,000 cubic meters
of rock excavated at the west heading

West heading:
Eastwards from Chorherrn, Lower Austria, mechanical heading using two tunnel boring
machines with hardrock drilling tools (D = 10.63 meters) 2 x 10,750 meters continuous
TBM heading, full section A = 87 square meters, creation of 21 crosscuts and four
turning niches, lined with liner segments and waterproof inner shell

Overground phase:
Earthworks and road construction, landscaping, recultivation; placement of approx.
1.2 million cubic meters of excavated material from the west heading over a length
of approx. 11 kilometers for the construction of a frontage road and for filling
a rail embankment.
More information about this project you can find in our Project sheet.
|
|
|
|
|
|
|
|
|